Unit No.1 was synchronized with maximum capacity of 180MW on Aug. 13, 2008, and is ready for the 168 hours trial run after necessary electrical tests. The commissioning of Unit No.2 has been started ...
Tuyen Quang 3x114MW Hydropower Project in Vietnam: Unit No.2 was put into Commercial Operation on 23rd of July. The PAC of Unit No.2 was obtained on 28th of July. The stator of generator of Unit No.3 ...
The rotor of generator of HPE Vietnam Cam Pha I 300MW Thermal Project was successful pl aced on 19th of August. By the time of this generator rotor placed, the project reached another payment ...